当前位置:网站首页>Information system project manager must recite the core examination site (48) selection of contract type
Information system project manager must recite the core examination site (48) selection of contract type
2022-07-22 15:43:00 【qiangge2015】
Kekeguo brings you the core key test site of soft exam information system project manager ( Forty eight ) Choice of contract type , Including mind map + The real question
【 Information system project manager core examination site 】 Contract type selection
One 、 A lump sum contract
1. Task and scope of work 、 The objectives and acceptance criteria are clear , And the project design has been provided with detailed details
2. Small quantities 、 Short construction period (1 During the year ), Small changes in construction environmental factors , The engineering conditions are stable
3. If the seller bears the cost risk
Two 、 Cost compensation contract
1. Nature of work 、 The scope of work is not clear or the project has high risks
2. If you buy a house and bear the cost risk
3、 ... and 、 The work and material contract
1. The nature of the work is clear , But the scope is not very clear , The work is not complicated , And need to sign a contract quickly
2. If both sides share the risk
Four 、 Unilateral contracts ( Purchase order )
Buy standard products , And it's not that much
【 Mind map of core test site 】
【 Core test site real questions 】
1. Outsourcing projects with unclear work scale or product definition , Generally, it should be ( ) In the form of .
A、 Fixed price contract B、 Cost compensation contract C、 Labor and material contracts D、 Purchase order
【 answer 】C
【 analysis 】 For outsourcing projects with unclear work scale or product definition, labor and material contracts are the best .
1. When the applicable product scope of total price contract I is clear ; The buyer's risk is small
2. Cost compensation contract : The scope of applicable products is not clear , Or when the project has high risks ; The seller has little risk
3. Labor and material contracts : Also known as unit price contract , It is a contract that combines the advantages of fixed total price and cost compensation . The quantity or duration is uncertain 、 Use when the work scale or product definition is not clear , Such as external experts 、 Find external support , It is conducive to the rapid signing of contracts .
2. For the contractor , Fixed unit price contract is applicable to ( ) Project .
A、 The construction period is long , The engineering quantity changes greatly B、 The construction period is long , The variation range of quantities is not too large
C、 Short construction period , The variation range of quantities is not too large D、 Short construction period , The engineering quantity changes greatly
【 answer 】C
【 analysis 】C For the contractor , If it is a fixed price contract , Short construction period , The risk that the variation of quantities is not too large is the smallest . Because if the construction period is long , The price of materials may change greatly ; The engineering quantity changes greatly , The scope is not clear , It is not suitable to use fixed price contracts . Be careful , A fixed unit price contract by title shall mean a fixed price contract , Instead of the quantity contract ( Material contract is also called unit price contract ).
3. A company agrees to order 3000 Meters high copper cable , Due to the construction unit , The construction period has been suspended for half a month , After the resumption of construction , The contractor cited the recent rise in copper prices as a reason , Ask the construction unit to compensate for the increased cost of purchasing cables , And require appropriate extension of construction period , In the following statement ,( ) That's right. .
A、 The construction unit shall compensate the contractor for the increased cost of purchasing cables
B、 The supervision unit should protect the legitimate interests of the contractor , Therefore, the claim for construction should be supported
C、 Claim is the embodiment of the interests of both parties to the contract , It can make the cost more reasonable
D、 Copper price rise is the project risk that the construction unit should bear , There should be no claim for compensation
【 answer 】D
【 analysis 】 A lump sum contract is a closed contract , Party A pays a fixed total price , If the range does not change , You can't add money normally . Although the construction period is suspended due to the construction unit , However, the copper price rise should be borne by the construction unit , Should not claim compensation for expenses ( Therefore, this contract is less risky for the buyer ). Therefore, when signing the lump sum contract , Party B should consider various situations and risks in advance .
4. A project is divided into several project packages when bidding , Contract out to different contractors . The contract that the Contractor shall sign with the tenderee after winning the bid belongs to ( ).
A、 Single project contract B、 Subcontract C、 Unit price contract D、 Cost incentive contract
【 answer 】A
【 analysis 】 Contracts can be divided into general contracts 、 Single project contract 、 Subcontract . The general contract is also called “ Turnkey contracting ”, The employer initiated the information system project from the beginning 、 demonstration 、 All tasks from construction to completion , To a qualified contractor . The single project contract is the contract letting party's different tasks of information system engineering construction , Contract out to different contractors . A subcontract is a part or parts of a project contracted by the general contractor , And then contract out to the sub contractor . It can be seen from the above that , The project is divided into several bid sections during bidding , Contract out to different contractors , After winning the bid, the Contractor shall sign a single project contract with the tenderee , So choose A. Note that there is no general contractor , So it's not a subcontract .
5. When preparing the project procurement plan , According to different purchase types , Different types of contracts are needed to cooperate ,( ) Including the actual cost paid to the seller , Plus some expenses usually used as the seller's profit
A、 Fixed price contract B、 Cost compensation contract C、 Labor and material contracts D、 Unit price contract
【 answer 】B
【 analysis 】 Advanced textbook Second Edition P284 Last but not least 9 That's ok .
1. Fixed total price is adopted for lump sum contract 1 , When the applicable product range is clear ; The buyer's risk is small
2. Cost compensation contract : Including the actual cost paid to the seller , Plus some expenses usually used as the seller's profit : The scope of applicable products is not clear , Or when the project has high risks ; The seller has little risk
3. Labor and material contracts : Also known as unit price contract , It is a contract that combines the advantages of fixed total price and cost compensation . The quantity or duration is uncertain 、 Use when the work scale or product definition is not clear , Such as external experts 、 Find external support , It is conducive to the rapid signing of contracts .
边栏推荐
- JMeter notes 1 | introduction and architecture of JMeter
- 9 good habits improve your happiness
- NiFi 1.16.3 生产使用的更新及BUG。
- v-if、v-for、列表的过滤与排序、强制绑定class和style、收集表单信息
- pyside2做个简易的浏览器
- 小乌龟上传远程仓库
- Record a summary of JMeter pressure test practice
- Chapter 3 - creating and maintaining MySQL data tables
- 记一次jmeter压测实战总结
- 2022.7.21 special matrix compression
猜你喜欢
C语言编写九九乘法表,实现不同三角形形状表格输出
Chapter 3 - creating and maintaining MySQL data tables
K-means clustering modeling and programming
Cloud native ide: the first general and powerful codeless development platform of IVX
df. Describe() detailed + usage + Example
MySQL installation failed. I don't know why
記一次jmeter壓測實戰總結
QT 动态dll的创建和调用
Halcon displays point clouds in TXT file format
玩转CANoe,博客目录大全
随机推荐
Leetcode 0128. longest continuous sequence
C语言实现通讯录详细教学
Exponential moving average method_ Baidu Encyclopedia
FPGA image processing learning face recognition
JS advanced ES6 implementation inheritance
BannerText(水印文本)
Aidl example
并查集框架
ROS learning (28) Web GUI
golang语言cli库
EACCES: permission denied, unlink ‘/usr/local/bin/code‘
Redis high availability principle master-slave sentinel cluster
Summary of URL rules for real-time streaming of Hikvision, Dahua and yushila
C语言编写九九乘法表,实现不同三角形形状表格输出
Cloud native ide: the first general and powerful codeless development platform of IVX
Monotonic stack framework
Nifi 1.16.3 updates and bugs used in production.
Enregistrer un résumé de la mesure de pression jmeter
The cluster planned in tidb includes 6 dB, 3 PD and 3 kV. When the application is disconnected, which address is it connected to?
牛客2022暑期集训第一场I题 Chiitoitsu 题解